Based in Edmonton, working across Alberta · Calls and email answered 24/7/365

1 800 716 8955contact@hsmcm.ca

Door Services

NBC(AE) 2023 · Section 3.8, Accessibility

Barrier-free doors and washrooms in Alberta

What the National Building Code – 2023 Alberta Edition asks of doors, power operators, hardware and universal washrooms, and what that means for your building.

The code

One provincial code, enforced locally

Alberta adopts its own edition of the National Building Code. The National Building Code – 2023 Alberta Edition has been in force since May 1, 2024, and Section 3.8, Accessibility sets out what makes a building accessible: barrier-free entrances and paths, doors and hardware, power door operators and universal washrooms.

Cities and towns don't write their own building codes. They, or an accredited safety codes agency, issue permits and inspect work under the provincial code. Some cities also publish guides on how they apply it.

Sources

Official references

What the code asks of doors

A summary of the Section 3.8 requirements that affect doors, hardware and washrooms. Article numbers refer to the National Building Code – 2023 Alberta Edition.

Power door operatorsArticle 3.8.2.7.
Power door operators are required at barrier-free entrances (including the inner door of a vestibule), at many doors along a barrier-free path to suites or rooms served by a public corridor, and at the entrance to any washroom with a barrier-free water closet. There are exceptions, so check how they apply to your building.
Operator controlsSentence 3.8.3.6.(6)
Push buttons must be on the barrier-free path, marked with the International Symbol of Access, and operable at two heights: 150 to 300 mm and 900 to 1 100 mm above the floor. Without safety sensors, the door must take at least 3 seconds to open fully and stop with a force of no more than 65 N.
Clear widthSentence 3.8.3.6.(2)
Doorways on a barrier-free path need a clear width of at least 850 mm with the door open.
Opening forceSentence 3.8.3.6.(8)
Without a power operator, an unlatched door must open with no more than 38 N for an exterior swing door and 22 N for an interior swing or sliding door. Closers have to be adjusted to meet this.
Door hardwareSentence 3.8.3.6.(4) and Clause 3.8.3.8.(1)(b)
Handles, latches and locks must be mounted 900 to 1 100 mm above the floor and work with one hand in a closed fist, without tight grasping or twisting. In practice that means levers, push/pull hardware or panic bars rather than knobs.
Barrier-free entrancesArticle 3.8.2.2.
All pedestrian entrances to a storey that must be barrier-free have to be barrier-free and connect to a barrier-free exterior path, with some exceptions such as service entrances. Where an entrance has more than one doorway, one of them has to meet the barrier-free door requirements.
Universal washroomsArticle 3.8.2.8.
Where washrooms are provided on a storey that needs a barrier-free path, at least one universal washroom is required, with exceptions such as washrooms inside residential suites. The universal washroom door must be lockable from inside with a closed fist, have an emergency release from outside, and, because the room has a barrier-free water closet, have a power door operator.

This is a plain-language summary, not the code itself. Requirements depend on the building's occupancy, size and whether the work is new construction or an alteration. Confirm them with your designer and the local authority having jurisdiction. More on barrier-free code.

Questions we hear a lot

Which building code applies in Alberta?

The National Building Code – 2023 Alberta Edition, in force since May 1, 2024. Accessibility requirements are in Section 3.8, Accessibility.

Do Calgary and Edmonton have their own building codes?

No. Both follow the provincial code and issue permits and inspections under it. Both cities publish guides explaining how they apply the accessibility section, and both have higher design standards for their own City-owned facilities.

Does the code apply to existing buildings?

Generally it applies to new construction and to the parts of a building being altered. A change of use or major renovation can trigger barrier-free upgrades, so check with your designer and permit office early.

Is this legal or code advice?

No. It's a plain-language summary to help you plan. Your designer and the local authority having jurisdiction have the final say.

Get a quote

Tell us about the door and what you need. Photos, drawings or a hardware schedule help us quote faster and more accurately.

Hours
Calls and email answered 24/7/365
Area
Across Alberta
Head
Suite 3400, 10180 101 St NW, Edmonton, AB T5J 3S4
St. Albert
175 Carleton Dr, St. Albert, AB T8N 7X9

Helpful to include

  • Photos of both sides of the door and its hardware
  • A close-up of the hinge edge and any labels
  • Width, height and handing if you know them

Download our brochure (PDF, 418 KB)